What Is Benching in Excavation?
Benching is a way to protect workers from cave-ins by cutting the sides of an excavation into one or more horizontal steps, usually with near-vertical faces between the steps.
How it works
OSHA lists benching as one kind of protective system, next to sloping, shoring and shields. Instead of one tall wall of soil, the sides step down in shelves. The steps are cut out of the ground being dug, so the hole ends up much wider at the top than at the bottom. That is why benching needs room, and why it is often impractical close to a foundation, a utility or a property line.
When protection is required
Under OSHA 1926.652(a), workers in an excavation must be protected from cave-ins. There are two exceptions: excavations made entirely in stable rock, and excavations less than 5 feet deep where a competent person examines the ground and finds no sign of a potential cave-in. Benching is one way to meet the rule. How big each step may be depends on the soil, so follow OSHA’s Subpart P soil tables or your engineer’s plan rather than guessing.
Planning information only, not engineering, legal or safety advice. Confirm requirements with your engineer, inspector or the OSHA text.
Limits that come with benching
OSHA’s Subpart P Appendix B shows benching for Type A and Type B soil in excavations 20 feet deep or less, with a maximum allowable slope of 3/4 to 1 for Type A and 1 to 1 for Type B. The appendix lists no benching configuration for Type C soil, so Type C work has to follow another option in 1926.652(b), such as a flatter sloped cut or an engineer’s design. For excavations deeper than 20 feet, sloping or benching must be designed by a registered professional engineer. Where a Type A excavation has an unsupported vertical lower portion, that vertical side is limited to 3 1/2 feet.
Common mistakes
- Stockpiling spoil on the top bench. OSHA 1926.651(j)(2) requires materials and equipment to be kept at least 2 feet from the edge of the excavation, or held back with retaining devices.
- Benching beside a structure. The wide top of a benched cut can undermine a nearby foundation. 1926.651(i) requires support such as shoring, bracing or underpinning where an adjoining structure is endangered.
- Forgetting the way out. Trench excavations 4 feet or deeper need a stairway, ladder, ramp or other safe means of egress, placed so workers travel no more than 25 feet laterally.
- Working in water. 1926.651(h) says not to work in accumulated or accumulating water without adequate precautions, and a competent person must monitor water removal equipment.
Related terms
Benching is one of several options under protective system. Compare it with shoring, and see excavation and trench for how OSHA defines the holes it applies to.
Source note: soil-type limits from OSHA 29 CFR 1926 Subpart P Appendix B; spoil, egress, water and adjacent-structure rules from 1926.651. Planning information only, confirm with your engineer, inspector or the OSHA text.
FAQ
Is benching the same as sloping?
No. Sloping cuts the wall back at a single incline. Benching cuts it into steps. OSHA defines them as separate systems.
Does a shallow hole need benching?
Not always. A hole under 5 feet can be exempt if a competent person finds no sign of cave-in potential. Anything deeper needs a protective system.
Who decides if the walls are safe?
A competent person must inspect the excavation daily before work starts and again after rainstorms or other events that raise the hazard (OSHA 1926.651(k)).
Sources
- OSHA 1926.650, excavation definitions
- OSHA 1926.652, protective systems
- OSHA 1926.651, specific excavation requirements
Related
Back to the full glossary. Related terms: Sloping and Trench box.
Questions about digging on your property? Contact Muthler Landscaping & Construction.