Job: [Project name] · Client: [Client]
Job #[ ] · Start [date] · Finish [date]
[Company]
Start from the numbers on your hardscape estimate, enter them as the estimate columns, then fill in actuals from receipts, time cards and fuel logs as the job runs. Variance is estimate minus actual, so a positive number means you came in under.
1. Cost table: estimated vs actual
| Code | Category | Description | Est qty | Est unit $ | Est total | Act qty | Act unit $ | Act total | Variance $ | Var % |
|---|---|---|---|---|---|---|---|---|---|---|
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | ||||||||
| Total cost | $0.00 | $0.00 | $0.00 | |||||||
2. Margin and variance
| Estimated cost | $0.00 |
| Actual cost so far | $0.00 |
| Cost variance (estimate minus actual; positive is under budget) | $0.00 |
| Gross profit (price minus actual cost) | $0.00 |
| Estimated gross margin (price minus estimated cost, divided by price) | |
| Actual gross margin (gross profit divided by price) | |
| Actual markup on cost (gross profit divided by actual cost) |
3. Billable hours
| Billable share of paid hours | |
| Non-billable hours (drive, rework, waiting) | 0 |
Nothing you type here is saved or sent. Copy it out or print it before you leave the page.
How to use the job cost spreadsheet
Set your cost codes once and use them on every job, so job number twelve compares cleanly with job number two. The starting codes in the table are labor, equipment, materials, subcontractors, disposal and fuel. Rename them to match how your bookkeeping tracks cost. Enter the estimate side from your hardscape estimate before the work starts, then log actuals weekly instead of at the end, when receipts are lost. When the job closes, use the real margin to adjust the next estimate. Bill the job from your invoice template and keep the proposal in the proposal template format.
Download or copy it
The Excel version (.xlsx) has the same columns with formulas, and it opens in Google Sheets. Or press “Copy as TSV” above and paste into cell A1 of a blank sheet.
Reading the variance
Variance here is estimate minus actual, so positive means under budget and negative means over. A line that is over every job is telling you the estimate is wrong, not that the crew is unlucky. Common culprits are drive time, disposal, fuel and base material that was thicker than planned.
Billable hours
For this sheet, billable hours are the hours priced into the contract, and paid hours are everything you paid for on the job. The gap is drive time, rework and waiting. Watching the ratio job to job shows where labor leaks.
Margin vs markup, with the arithmetic
Margin is profit as a share of the price. Markup is profit as a share of the cost. They are different numbers for the same dollars, and mixing them up is how contractors underprice.
- Markup = (price minus cost) / cost
- Margin = (price minus cost) / price
- Margin = markup / (1 + markup)
- Markup = margin / (1 – margin)
- Price for a target margin = cost / (1 – margin)
Worked example on $1,000 of cost
| Method | Price | Profit | Margin | Markup |
|---|---|---|---|---|
| 25% markup | $1,250.00 | $250.00 | 20.00% | 25.00% |
| 30% markup | $1,300.00 | $300.00 | 23.08% | 30.00% |
| 50% markup | $1,500.00 | $500.00 | 33.33% | 50.00% |
| 20% margin | $1,250.00 | $250.00 | 20.00% | 25.00% |
| 25% margin | $1,333.33 | $333.33 | 25.00% | 33.33% |
| 30% margin | $1,428.57 | $428.57 | 30.00% | 42.86% |
So a 25% markup is a 20% margin: $1,000 x 1.25 = $1,250, profit is $250, and $250 / $1,250 = 20%. If you wanted a 25% margin and added 25% markup instead, you would price at $1,250 where the target price is $1,333.33, which is $83.33 short on every $1,000 of cost. Calculate the price with cost / (1 – margin), as the estimate template does.
Related
Our guide on how to estimate a paver patio covers the takeoff side. Use the hardscape calculators for quantities, and see every free form on the contractor templates page. If drawing and measuring is the bottleneck, we draw plans for contractors under your logo.
Sources: the margin and markup figures above are arithmetic, computed directly from the formulas shown (price = cost x (1 + markup), or cost / (1 – margin)); no outside source is needed. Cost codes and the billable-hours definition are suggestions, not an accounting standard. Check your setup with your CPA.
Questions
What is a job cost spreadsheet?
A sheet that compares what a job was estimated to cost with what it actually cost, by cost code, so you can see variance and real gross margin after the job.
Is 25% markup the same as 25% margin?
No. A 25% markup on cost is a 20% margin on price. A 25% margin needs a 33.33% markup.
How do I calculate a price from a target margin?
Divide your cost by one minus the margin. For $1,000 of cost and a 25% margin, that is $1,000 / 0.75 = $1,333.33.
Can I use this in Excel or Google Sheets?
Yes. Download the .xlsx, which opens in both, or press Copy as TSV and paste into a blank sheet.
Template by Groundwork Design Co., the design studio of Muthler Landscaping & Construction LLC, Lock Haven, PA. A starting point, not legal or tax advice: have your attorney and CPA review it before you rely on it.