Texas Mechanics Lien Deadlines for Residential Jobs
On a Texas home project, an unpaid contractor has until the 15th day of the third month after the month the job was completed, terminated or abandoned to file a mechanics lien affidavit, and subcontractors and suppliers must first send a notice of claim by the 15th day of the second month after each month of unpaid work. A lien on a homestead also needs a written contract signed before work starts, by both spouses if the owner is married, and filed with the county clerk. These are the rules in Chapter 53 of the Texas Property Code for contracts signed on or after January 1, 2022, when House Bill 2237 rewrote the lien law.
Quick answer
- Sub and supplier notice: 15th day of the 2nd month after the month the work or materials were provided
- Lien affidavit: 15th day of the 3rd month after the job ends (original contractor) or after the claimant last furnished work (subs and suppliers)
- Copy to owner: Within 5 days after filing
- Homestead: Written contract signed before work, by both spouses, filed with the county clerk, plus required notice language
- Retainage: Owner holds 10 percent during the work and for 30 days after completion
- Lawsuit deadline: 1 year after the last day the affidavit could be filed
Which Texas lien rules apply to your project?
House Bill 2237 took effect January 1, 2022 and applies only to original contracts entered into on or after that date; older contracts stay under the prior law (H.B. 2237, Sections 37 and 38). A home job contracted today falls under the new rules.
Texas sets shorter deadlines for residential construction projects than for commercial ones, and extra requirements when the property is a homestead. Two procedural rules apply to every notice (Tex. Prop. Code 53.003):
- Delivery: in person, by certified mail, or by another traceable private delivery service that can confirm receipt. A notice the person actually receives counts however it was sent.
- Weekends and holidays: if a deadline lands on a Saturday, Sunday or legal holiday, it moves to the next day that isn’t one.
Texas mechanics lien deadlines for residential projects
| Who | Step | Deadline on a residential project | Law |
|---|---|---|---|
| Subcontractor or supplier | Notice of claim for unpaid labor or materials, to the owner and the original contractor | 15th day of the 2nd month after the month the labor or materials were provided | 53.056 |
| Sub or supplier owed retainage | Notice of contractual retainage claim, to the owner and the original contractor | Earlier of 30 days after its own contract ends or 30 days after the original contract is terminated or abandoned | 53.057 |
| Original contractor | Lien affidavit filed with the county clerk | 15th day of the 3rd month after the month the original contract was completed, terminated or abandoned | 53.052(a) |
| Subcontractor or supplier | Lien affidavit filed with the county clerk | 15th day of the 3rd month after the month it last provided labor or materials | 53.052(c) |
| Retainage claimant | Lien affidavit for retainage | 15th day of the 3rd month after the month the original contract was completed, terminated or abandoned | 53.052(d) |
| Anyone who files | Copy of the affidavit to the owner (and to the original contractor, if the filer isn’t it) | Within 5 days after filing | 53.055 |
| Lien claimant | Lawsuit to foreclose the lien | 1 year after the last day the affidavit could have been filed; a recorded written agreement with the owner can extend it to 2 years after filing | 53.158 |
An example of how the monthly clock works: a sub who wasn’t paid for March work must send its notice of claim by May 15, and a separate notice for each later unpaid month. If the original contract wraps up in June, the original contractor’s affidavit is due September 15. On non-residential projects each of those deadlines is one month later.
The affidavit is filed in the county where the property is, and the notice of claim must be in substantially the statutory form, which can include an invoice. The optional past-due notice a sub may send the general contractor under 53.056(a-4) doesn’t replace the notice of claim to the owner.
What are the homestead lien rules in Texas?
Homesteads get extra protection. Tex. Prop. Code 53.254 adds conditions a lien claimant has to meet:
- Written contract first: the contractor and owner must sign a written contract stating the terms before any materials are furnished or labor is performed.
- Both spouses: if the owner is married, both spouses have to sign it.
- Filed with the county clerk: the contract must be recorded in the county where the homestead is. An original contractor’s contract also benefits its subs and suppliers.
- Affidavit warning: a homestead lien affidavit must start with a conspicuous notice in at least 10-point bold type stating that it is not a lien, only an affidavit claiming one.
- Owner statement: a sub’s or supplier’s notice of claim on a homestead must include the statutory statement explaining that the owner can avoid the lien by withholding enough to cover the claim and reserving 10 percent of the contract price.
Missing any of these is one of the listed grounds for the owner to ask a court to remove the lien on a summary motion (53.160). For contractors, the practical rule is to have both spouses sign before you deliver anything, and record the contract.
How Texas homeowners protect themselves from liens
Texas limits an owner’s exposure to what the owner holds back, as long as the owner follows the rules:
- 10 percent retainage: the owner must hold back 10 percent of the contract price, or of the value of work done, during the work and for 30 days after it is completed (53.101).
- Withhold after a notice: once a notice of claim arrives, the owner should hold back enough of the contractor’s payments to cover it. Payments made before the owner could withhold aren’t the owner’s risk, apart from retainage it failed to keep, and payments made after a notice create liability only if the lien is secured and reduced to a final judgment (53.084).
- Disclosure and sub list: before signing, the contractor gives a statutory disclosure statement, and before work starts a list of subs and suppliers, updated within 15 days of changes (53.255, 53.256).
- Bills-paid affidavit: final payment on a residential contract is conditioned on the contractor’s sworn affidavit that everyone has been paid, or a list of who hasn’t (53.259).
- Summary removal: an owner can move to remove a lien that missed a notice or filing deadline, lacks homestead requirements or was waived. Parties get at least 30 days’ notice of the hearing (53.160).
Do Texas lien waivers have to be on a statutory form?
Yes. A waiver and release of lien rights is unenforceable unless it substantially follows one of the four forms in 53.284 and is signed by the claimant or its agent (53.281):
- Conditional, progress payment and conditional, final payment: used before the money arrives; they take effect only once the check is endorsed and paid by the bank.
- Unconditional, progress payment and unconditional, final payment: for after payment is received. Both open with a bold warning that the signer is giving up rights and should use a conditional form if not yet paid.
Progress-payment waivers don’t cover unpaid retention or pending changes. Contractors should sign conditional forms until funds clear; owners should collect waivers from the general contractor and from every sub and supplier on the list.
Sources
- Tex. Prop. Code 53.003, 53.052, 53.055, 53.056, 53.057 and 53.158
- Tex. Prop. Code 53.084, 53.101 and 53.160
- Tex. Prop. Code 53.254, 53.255, 53.256 and 53.259
- Tex. Prop. Code 53.281 and 53.284
- H.B. 2237 (2021), enrolled text and the official Texas Property Code Chapter 53
Last checked November 14, 2026.
Common questions
How long do you have to file a mechanics lien in Texas?
On a residential project, the lien affidavit is due by the 15th day of the third month after the month the original contract was completed, terminated or abandoned, or, for a sub or supplier, after the month it last provided work or materials. On other projects the deadline is the 15th day of the fourth month. A copy goes to the owner within 5 days after filing.
When must a subcontractor send notice in Texas?
On a residential project, a subcontractor or supplier must send a notice of claim to the owner and the original contractor by the 15th day of the second month after the month the unpaid labor or materials were provided. On other projects it is the 15th day of the third month.
Can a contractor put a lien on a homestead in Texas?
Yes, but only if a written contract was signed before any work or materials were provided, signed by both spouses if the owner is married, and filed with the county clerk. The lien affidavit also needs a bold notice that it is not a lien, and a sub’s notice of claim must include the statutory statement to the owner.
Do Texas lien waivers have to use a specific form?
Yes. A lien waiver is unenforceable unless it substantially complies with one of the four statutory forms: conditional or unconditional, for a progress or final payment. Conditional waivers take effect only when the payment clears.
This is a plain-English summary, not legal advice.
See every Texas building, digging and contractor rule on our Texas guide. Related: Texas contractor license rules · Texas building code · Texas permits for decks, sheds and retaining walls · Mechanics lien deadlines by state.
Groundwork Design Co. · designed by builders
Plans drawn for Texas’s rules
Groundwork Design Co. draws patios, walls, decks and planting plans to scale for any U.S. home, with the layout, sizes and materials any local contractor can price.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Texas Mechanics Lien Deadlines for Residential Jobs,” https://muthlerlandscaping.com/state-guides/texas/mechanics-lien/ (page updated November 15, 2026).
Get an email when your state’s rules change
We re-check every entry against official sources. Tell us your state and we’ll email you when something changes.