Steel erection scope, definitions and site layout: OSHA 1926.750 to 1926.752

Quick answer: Subpart R of OSHA’s construction standards covers steel erection. Section 1926.750 sets the scope and lists what is excluded (transmission towers, communication and broadcast towers, and tanks), 1926.751 defines the terms used in the subpart, and 1926.752 puts duties on the controlling contractor: written notification that concrete and mortar have reached 75 percent of intended minimum compressive design strength or enough strength for erection loads, access roads, a firm, graded and drained storage and operating area, pre-planned hoisting, and a site-specific erection plan when alternate means and methods are used.

This page goes through 29 CFR 1926.750, 1926.751 and 1926.752 as shown on the Cornell Legal Information Institute, checked November 23, 2026. Verify every figure and definition against the current source at ecfr.gov before relying on it. Where the text is silent, we say it is not stated. These three sections are only the front end of Subpart R. For related topics, see our pages on cranes and power line safety, rigging equipment and the fall protection duty.

Section 1926.750: scope and application

PartWhat the text says
(a) Purpose, application and exclusionsThe subpart sets requirements to protect employees from the hazards of steel erection in the construction, alteration and repair of single and multi-story buildings, bridges and other structures where steel erection occurs. It applies to employers engaged in steel erection unless a provision says otherwise. It does not cover electrical transmission towers, communication and broadcast towers, or tanks. Those are the only exclusions listed.
Note to (a): covered structuresA long, non-exhaustive list of structure types where steel erection may occur, including buildings, bridges, stadiums, power plants, conveyor systems, platforms, cranes and craneways, and amusement park structures. The list is introduced as including but not limited to those items, so it does not limit coverage to the items named.
(b)(1) Core activitiesSteel erection activities are hoisting, laying out, placing, connecting, welding, burning, guying, bracing, bolting, plumbing and rigging structural steel, steel joists and metal buildings. They also include installing metal decking, curtain walls, window walls, siding systems, miscellaneous metals and ornamental iron, and moving point-to-point while performing these activities.
(b)(2) Related activitiesListed activities such as rigging, hoisting, dismantling, grinding, sealing and caulking are covered when they occur during steel erection and are part of it. The materials named include structural steel, ferrous and non-ferrous metals, glass, plastics, concrete on steel frames, and building components such as stairs, railings, doors, windows and skylights. The condition is that the activities be a part of steel erection activities.
(c) Controlling contractorControlling contractors have duties under the subpart, including those in 1926.752(a) and (c), 1926.755(b)(2), 1926.759(b) and 1926.760(e). The list is introduced as including but not limited to those provisions.

What section 1926.750 does not state

  • The text of definitions such as employer, employees, steel erection and controlling contractor. They are linked on the page, and the next section, 1926.751, holds the definitions.
  • Substantive safety requirements. The page covers scope only.
  • The text of the cross-referenced duties in 1926.752, 1926.755, 1926.759 and 1926.760.
  • Other exceptions. Paragraph (a) says provisions may specify otherwise, but the page does not identify them.
  • Effective dates, amendment history or authority citations.

Section 1926.751: definitions

Section 1926.751 defines 46 terms used in Subpart R. The paraphrases below are our own wording.

Terms most relevant to the site layout section

TermMeaning, paraphrased
Controlling contractorThe prime, general or construction manager contractor, or other entity with overall responsibility for a project’s planning, quality and completion.
Competent personSomeone who can identify existing and predictable hazards in the work environment and has authority to take prompt corrective action. The term is also defined in 1926.32.
Qualified personSomeone who, through a recognized degree, certificate, professional standing, or extensive knowledge, training and experience, has shown the ability to solve problems related to the work or project. 1926.32 also defines this term.
Steel erectionConstructing, altering or repairing steel buildings, bridges and other structures, including installing metal decking and planking used during erection.
Structural steelSteel members, or members of substitute material such as fiberglass, aluminum or composites. The list includes joists, joist girders, purlins, columns, beams, trusses, splices, seats, metal decking, girts, all bridging, and cold-formed framing integrated with the steel frame.
Hoisting equipmentCommercially made lifting equipment, such as cranes, derricks, tower cranes, gin poles and gantry systems, that lifts a load of known weight. A come-a-long is excluded.

Other defined terms with numbers

TermMeaning, paraphrased
Decking holeA gap in a floor, roof or other working surface that is more than 2 inches but less than 12 inches in its greatest dimension, measured on its least dimension. Pre-engineered holes in cellular decking for wires or cables are excluded.
OpeningA gap of 12 inches or more in its least dimension in a walking or working surface. Skylights and smoke domes that do not meet the strength requirements of 1926.754(e)(3) count as openings.
Critical liftA lift that either exceeds 75 percent of the crane’s or derrick’s rated capacity, or requires more than one crane or derrick.
Multiple lift riggingA wire rope rigging assembly that attaches up to five independent loads to a crane’s hoist rigging.
PostA mostly vertical member that weighs 300 pounds or less and is axially loaded, or is laterally restrained by the member above it. Posts support landings, wall framing and mezzanines.
Steel joistAn open-web secondary load-carrying member of 144 feet or less, designed by the manufacturer. Structural steel trusses and cold-formed joists are excluded.
Unprotected sides and edgesAny side or edge of a working surface, except at access points, lacking a wall or guardrail at least 39 inches high.

Additional definitions

  • Column: a load-carrying vertical member that is part of the primary framing. Posts are excluded.
  • Connector: a worker who, using hoisting equipment, places and connects structural members or components.
  • Controlled decking zone: an area where certain work, such as initial decking placement, may occur without guardrails, personal fall arrest, fall restraint or safety net systems, provided access is controlled.
  • Fall restraint system: a system that prevents the user from falling any distance, using a body belt or harness with an anchorage, connectors and other necessary equipment, typically including a lanyard.
  • Personal fall arrest system: a system that stops a worker’s fall from a working level, made of an anchorage, connectors and a body harness, plus optional components. Body belts are prohibited for fall arrest.
  • Positioning device system: a body belt or harness rigged so a worker can be supported on a vertical surface, such as a wall or column, while keeping both hands free.
  • Leading edge: the unprotected edge of a floor, roof or formwork that moves as more sections are added.
  • Permanent floor: a structurally complete floor at any level, including slab on grade.
  • Project structural engineer of record: the licensed professional responsible for the structural steel design, whose seal appears on the contract documents.
  • Metal decking: cold-rolled structural metal panels with parallel ribs, including roof and floor decks, bar gratings, checker plate and similar products.
  • Rigging terms: a choker is a wire rope or synthetic fiber assembly used to attach a load to a hoisting device; a headache ball is a weighted hook that attaches loads to a crane’s hoist line.

What section 1926.751 does not state

  • Definitions for steel erector and anchor bolt.
  • The full text of 1926.32, cited for the competent person and qualified person definitions.
  • The 1926.754(e)(3) strength requirements referenced in the opening definition.
  • Any text from other Subpart R sections.

Section 1926.752: site layout, erection plan and construction sequence

ParagraphWhat the text says
(a) Approval to begin steel erectionBefore authorizing steel erection to begin, the controlling contractor must ensure the steel erector receives written notifications. Under (a)(1), concrete in footings, piers and walls, and mortar in masonry piers and walls, must have reached either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection, based on an appropriate ASTM standard test method using field-cured samples. Under (a)(2), any repair, replacement or modification of anchor bolts must have been done in accordance with 1926.755(b).
(b) Commencement of steel erectionA steel erection contractor may not erect steel until it has received written notification that the concrete or mortar meets the strength criteria in (a)(1).
(c)(1) Access roadsThe controlling contractor must ensure adequate roads into and through the site for the safe delivery and movement of derricks, cranes, trucks, other necessary equipment and the material being erected, along with means and methods for controlling pedestrian and vehicle traffic. Roads outside the construction site are excepted.
(c)(2) Storage and operating areaA firm, properly graded and drained area, readily accessible to the work, with enough space for safe storage of materials and safe operation of the erector’s equipment.
(d) Pre-planning of overhead hoistingAll steel erection hoisting operations must be pre-planned to ensure the requirements of 1926.753(d) are met.
(e) Site-specific erection planIf an employer, because of site-specific conditions, chooses alternate means and methods that protect employees under 1926.753(c)(5), 1926.757(a)(4) or 1926.757(e)(4), a qualified person must develop a site-specific erection plan, and the plan must be available at the work site. Appendix A to the subpart provides guidelines for establishing the plan.

What section 1926.752 does not state

  • The definitions of controlling contractor, qualified person, employer and competent person. Those are in 1926.751.
  • Which ASTM standard applies, how many samples are needed, or the testing frequency.
  • Whether the written notifications must follow a specific format, timing or signature requirement, or who retains them.
  • Whether the site-specific erection plan must be in writing, what it must contain, or how it is approved.
  • Numeric standards for roads, such as width, load capacity or grade, or for storage area drainage and grading.
  • Any requirement to document the hoisting pre-planning in paragraph (d).
  • The content of Appendix A, which is referenced.
  • Penalties, enforcement details or compliance deadlines.

Cross-references to other sections

Where mentionedSection referencedWhy, per the text
1926.750(c)1926.752(a), (c); 1926.755(b)(2); 1926.759(b); 1926.760(e)Listed as examples of controlling contractor duties
1926.752(a)(2)1926.755(b)Standard for anchor bolt repairs, replacements and modifications
1926.752(d)1926.753(d)Requirements that hoisting pre-planning must ensure are met
1926.752(e)1926.753(c)(5); 1926.757(a)(4); 1926.757(e)(4)Alternate means and methods that trigger the site-specific erection plan
1926.7511926.754(e)(3)Strength requirements for skylights and smoke domes in the opening definition
Planning information only. This page summarizes public regulation text and is not engineering, legal or safety advice. Check the current CFR text before relying on any number here, and talk to a competent person or engineer about your own site.

Sources

SourceUsed for
29 CFR 1926.750, Scope, application, and definitions applicable to this subpart (Cornell LII)Scope, exclusions and controlling contractor cross-references
29 CFR 1926.751, Definitions (Cornell LII)Defined terms summarized above
29 CFR 1926.752, Site layout, site-specific erection plan and construction sequence (Cornell LII)Paragraphs (a) through (e) summarized above

Checked Nov. 23, 2026. Verify against the current source at ecfr.gov before relying on details.

Related

Cranes and power line safety · Rigging equipment and slings · Fall protection duty · All PA site work regulations

Talk to us about your project

FAQ

What concrete strength does 1926.752 require before steel erection starts?

Paragraph (a)(1) says concrete in footings, piers and walls, and mortar in masonry piers and walls, must have reached 75 percent of the intended minimum compressive design strength or sufficient strength to support erection loads, based on an appropriate ASTM standard test method using field-cured samples.

Who must provide access roads and a storage area under 1926.752?

Paragraph (c) says the controlling contractor must ensure adequate access roads and a firm, properly graded and drained storage and operating area are provided and maintained.

What does Subpart R say it does not cover?

Paragraph 1926.750(a) says the subpart does not cover electrical transmission towers, communication and broadcast towers, or tanks.

When is a site-specific erection plan required under 1926.752(e)?

Paragraph (e) says it applies when an employer, because of site-specific conditions, chooses alternate means and methods under 1926.753(c)(5), 1926.757(a)(4) or 1926.757(e)(4). A qualified person must develop it and it must be available at the work site.

General information only, not legal or safety advice. Employers must follow the current OSHA standard and applicable Pennsylvania rules. Source pages checked Nov. 23, 2026.