Lead in construction: what OSHA 1926.62 requires when work disturbs lead
Quick answer: OSHA’s lead in construction standard, 29 CFR 1926.62, sets a permissible exposure limit of 50 micrograms of lead per cubic meter of air as an 8-hour average, with an action level of 30. Work such as demolition, renovation, scraping, sanding or torch cutting on lead-coated surfaces can trigger interim protections before any air testing is done.
Who and what the rule covers
Section 1926.62 applies to construction work where employees may be exposed to lead. The scope paragraph lists demolition or salvage of structures that contain lead, removal or encapsulation of lead, new construction, alteration, repair or renovation, installation of lead-containing products, lead contamination cleanup, on-site transport, storage and disposal of lead materials, and maintenance operations that go with those jobs. For a contractor working on older homes, porches, windows, siding, metal railings or steel, the question is not whether the company is a lead abatement firm. The question is whether the task disturbs lead and exposes workers.
The rule defines lead as metallic lead, all inorganic lead compounds and organic lead soaps. It also defines a competent person as someone able to identify existing and predictable lead hazards and authorized to take prompt corrective action.
Exposure limits
| Term | Value |
|---|---|
| Permissible exposure limit (PEL) | 50 micrograms per cubic meter, 8-hour time-weighted average |
| Action level | 30 micrograms per cubic meter, 8-hour time-weighted average, measured without regard to respirators |
| Extended shifts | Allowable exposure is 400 divided by the hours worked; a 10-hour shift is 40 micrograms |
Interim protection: assumed exposure before testing
An employer must determine whether any worker may be at or above the action level, using personal sampling, prior monitoring from the last 12 months when conditions closely match, or objective data. Paragraph (d)(2) goes further and says that certain tasks are presumed to exceed the PEL until an assessment shows otherwise.
- Where lead coatings are present, manual demolition, manual scraping, manual sanding, heat gun work and power tool cleaning with dust collection are treated as above the PEL, though not above 10 times the PEL. Spray painting with lead paint is in the same group.
- Lead mortar use, lead burning, rivet busting, power tool cleaning without dust collection, cleanup with dry expendable abrasives and abrasive blasting enclosure movement are treated as above 500 micrograms per cubic meter.
- Abrasive blasting, welding, cutting and torch burning on structures with lead coatings are treated as above 2,500 micrograms per cubic meter, which is 50 times the PEL.
Until the assessment shows exposure at or below the PEL, the interim package applies: respirators, protective clothing and equipment, change areas, handwashing facilities, biological monitoring, and training. Employees must be told of their results within 5 working days.
Controls, written program and respirators
Employers must use engineering and work practice controls, including administrative controls, to reduce exposure to the PEL where feasible, and supplement them with respirators where needed. A written compliance program is required before the job starts. It must describe the lead-emitting activities, the compliance methods, the monitoring data and a schedule, and a competent person must inspect frequently. It must be updated at least annually. Respirators are required above the PEL, where controls are not enough, on employee request, and during interim protection. The respirator program follows 29 CFR 1910.134, with HEPA filters on air-purifying respirators and a full facepiece where lead aerosols may irritate the eyes or skin.
Protective clothing, housekeeping and hygiene
- Clothing: coveralls, gloves, hats, shoe coverings and face or eye protection are provided at no cost where exposure is above the PEL. Clothing is cleaned and dried weekly, or daily where exposure without a respirator exceeds 200 micrograms per cubic meter. Blowing or shaking contaminated clothing is prohibited.
- Housekeeping: surfaces are kept as free of lead as practicable. Vacuuming with HEPA filters or other low-dispersion methods comes first, and dry sweeping, shoveling or brushing is allowed only if vacuuming has been tried and found ineffective. Compressed air may be used only with capture ventilation.
- Hygiene: no food, drink, tobacco or cosmetics where exposure is above the PEL. Provide a clean change area with separate storage for work and street clothes, handwashing facilities, a lead-free-as-practicable eating area, and showers where feasible. Workers must wash before eating.
Medical surveillance and removal
Blood lead and zinc protoporphyrin testing is part of initial surveillance for employees exposed at or above the action level on any day. A full medical surveillance program applies to employees at or above the action level for more than 30 days in any consecutive 12 months, under a licensed physician and at no cost to the employee. Testing is every 2 months for the first 6 months and every 6 months after that, and every 2 months if a result was 40 micrograms per deciliter or higher until two consecutive results fall below 40. An employee at 50 micrograms per deciliter or higher on a periodic or follow-up test is removed from lead exposure, with medical removal protection benefits of up to 18 months, and returns after two consecutive results below 40. Prophylactic chelation is prohibited.
Training, signs and records
Workers exposed at or above the action level on any day need training before assignment and at least annually, plus hazard communication covering lead’s health effects. Areas above the PEL carry DANGER / LEAD WORK AREA signs. Exposure records and medical records are kept as the standard specifies, and objective data records are kept at least 30 years.
Sources
Sources checked Nov. 23, 2026.
Related
Hazard communication · Asbestos in construction, 1926.1101 · Silica rule · All PA site work regulations
FAQ
What is the OSHA lead exposure limit in construction?
The permissible exposure limit under 1926.62 is 50 micrograms of lead per cubic meter of air as an 8-hour time-weighted average, and the action level is 30.
Do I have to test the air before starting lead work?
Not always. Paragraph (d)(2) presumes certain tasks, such as manual scraping or sanding of lead coatings, exceed the PEL, so interim protections apply until an assessment shows otherwise.
When is medical surveillance required?
A full program applies to employees at or above the action level for more than 30 days in any consecutive 12 months, and initial blood lead testing applies to those exposed at or above the action level on any day.
Can I dry sweep lead dust?
Only if vacuuming or another low-dispersion method has been tried and found ineffective; HEPA vacuuming comes first, and compressed air needs capture ventilation.
General information only, not legal or safety advice. Employers must follow the current OSHA standard and applicable Pennsylvania rules. Muthler Landscaping & Construction LLC, 913 Bellefonte Ave, Lock Haven, PA 17745, (570) 397-9800, PA HIC #PA212584. Source pages checked Nov. 23, 2026.