What Is an Erosion Control Blanket? Anchoring, Overlap and Staples
An erosion control blanket is a rolled mat of fiber, usually held in place with netting and anchored with staples or stakes, that covers bare soil on a slope or in a channel while seed grows. It protects the soil and seed from rain and flowing water in the weeks before vegetation takes over. It only works when it stays in firm contact with the ground.
Erosion control blanket and the terms around it
- Erosion control blanket: the term used on a North Dakota DOT detail sheet that shows single net and double net blankets. The Federal Highway Administration and the Iowa SUDAS drawings call the installed product a rolled erosion control product, or RECP. Those drawings appear to describe the same kind of rolled cover, but they are separate documents.
- Matting: according to EPA, jute, coir or other wood fibers formed into sheets, which it says are more stable than loose mulch.
- Netting: EPA lists jute, wood fiber, plastic, paper or cotton netting that holds mulch and matting in place and can stabilize soil on its own.
- Anchor trench: the small trench at the top of the roll where the blanket end is buried and secured. See the drawings below for dimensions.
- Hydroseeding: a spray-applied alternative for seeding slopes. Compare it in our hydroseeding entry.
Why it matters on a job
Seed on a bare slope can wash off in the first heavy rain. EPA says matting and netting stabilize surfaces and temporarily hold seed, fertilizer and topsoil while vegetation establishes, and that matting can be placed on slopes to protect soil and seedlings while vegetation grows through it. The same fact sheet says the material has to keep firm, continuous contact with the soil, through anchoring or cover material. Without that contact, EPA says erosion occurs underneath.
That makes the grading step as important as the product. FHWA’s drawing says to grade, smooth and compact the slope and to remove rocks, trash and other debris that would keep the blanket from lying flat on the ground. It also says not to track the slope face. In Pennsylvania, blankets also show up in stormwater rules. The PA DEP erosion and sediment control FAQ says a blanket used within 100 feet of an inlet filter bag, together with that bag, can reach an efficiency rating for exceptional value watersheds. It adds that blankets are not assigned a sediment removal rating of their own, and it gives no design standard for them.
What the installation drawings say
Three public drawings show how agencies detail a slope blanket. Their numbers differ, which is the main lesson: the product manufacturer’s instructions and your project specification set the actual values.
- FHWA Federal Lands drawing E629-01: the lower blanket sits in a trench 6 inches deep by 6 inches wide. Edges overlap 3 inches and ends overlap 6 inches. Fasteners go on 12 inch centers, with a double row at an erosion stop. Wood stakes cut from 1 by 3 inch stock are shown at 36 to 60 inch intervals, and typical staples are 11 gauge wire. The blanket is unrolled down the slope in the direction of flow, anchored at the top and not stretched.
- North Dakota DOT slope detail (2017 file date): 8 inch, 11 gauge wire U staples at 3.8 staples per square yard, in two staggered rows 4 inches apart, spaced 6 inches on center and within 6 inches of the blanket edge. Adjacent blankets overlap at least 6 inches. Splices go at least 24 inches before the toe of the slope, and the blanket extends 24 inches beyond the toe or to the edge of vegetation, whichever is closer. If ditch flow is present, it extends 24 inches upslope.
- Iowa SUDAS figure 9040.103 (2025): anchor trenches at the upslope and terminal ends, backfilled with compacted soil, with a minimum anchor density of 1.3 anchors per square yard and staples at 1 foot on center. The figure also shows staggered double rows of staples at 4 inches.
The North Dakota sheet lists the installation order: prepare a smooth slope, amend the soil and seed, dig the anchor trench and set the native soil aside, secure the blanket in the trench, replace the soil, and staple so there are no gaps between blanket and soil. It also says to staple while unrolling to limit walking on the blanket. FHWA’s notes add that topsoil and turf establishment go in where the contract requires, with seed and fertilizer applied as the manufacturer recommends.
Limits and maintenance
EPA’s fact sheet lists limits that apply to geotextiles and fabrics more broadly. Synthetic materials do not break down naturally, many degrade quickly under sunlight, wind can displace them, and poor selection, design or installation can greatly reduce effectiveness. It says to address cracks, tears or breaches right away and to add cover material or staking where the material has separated from the ground. It does not give an inspection frequency. EPA also says matting and netting typically cost about $1 to $4 per square yard, with the range depending on material, strength, thickness and durability. That is an EPA figure from 2021 and not a local price.
None of the documents cited here gives a slope limit for blankets, so we do not state one here. Product data sheets usually specify the slopes and flow conditions each product is rated for, and that sheet is the place to check.
Common mistakes
- Rolling it out over rocks and debris. FHWA says to clear them so the blanket lies flat against the ground. Bridging leaves a gap where water can run underneath.
- Stretching the blanket. FHWA says not to stretch it as it is unrolled down the slope.
- Skipping the anchor trench. Every drawing above starts the roll in an anchor trench at the top.
- Copying one agency’s staple count onto another product. The three drawings differ on overlap and fastener spacing.
- Leaving tears unrepaired. EPA says to address tears and breaches immediately.
Erosion control blanket FAQ
Is an erosion control blanket the same as matting?
They overlap. EPA describes matting as jute, coir or other wood fibers formed into sheets and netting as the layer that holds mulch and matting in place. DOT drawings use the names blanket and rolled erosion control product for the installed roll.
How much should blankets overlap?
It depends on the drawing. FHWA shows a 3 inch edge overlap and a 6 inch end overlap, and North Dakota shows a 6 inch minimum overlap. Follow the manufacturer and the project specification.
How are blankets anchored?
With an anchor trench at the top and staples or stakes across the face. The drawings show wire staples with spacing from 6 inches to 12 inches on center, plus wood stakes in the FHWA detail.
Does Pennsylvania give a sediment removal rating for blankets?
No. The PA DEP FAQ says blankets are not assigned a sediment removal rating, though a blanket used within 100 feet of an inlet filter bag can count toward an efficiency rating in exceptional value watersheds.
Sources
- U.S. EPA, NPDES BMP Fact Sheet: Geotextiles, Matting and Netting (EPA-832-F-21-028T, December 2021)
- FHWA Federal Lands Highway, Standard Drawing E629-01: Slope Stabilization with Rolled Erosion Control Product
- North Dakota DOT, Slope Erosion Control Blanket Installation Details
- Iowa SUDAS Standard Specifications, Figure 9040.103: RECP Installation on Slopes
- Pennsylvania DEP, Erosion and Sediment Control FAQ
These are agency drawings from other jurisdictions, not Pennsylvania standards. Verify against the current source and the product data sheet before you rely on any number.
Keep reading
- Hardscape and Site Work Glossary
- Related terms: hydroseeding, surface roughening, check dam, geotextile fabric and vegetated swale
Stabilizing a slope in central PA? Contact Muthler Landscaping & Construction for a straight answer. Planning information, not engineering advice.