Equipment guides · Layout · Levels and stakes
Laser levels and grade stakes for patio layout
A patio that drains and sits at the right height starts before the first shovel of gravel. Grade stakes record how much to cut or fill, string lines and a level reference carry that height across the site, and the slope target tells you how much fall to build in.
Unilock recommends a slope of 1.5 to 2% and sets base gravel to string lines. At 2%, that is about 1/4 in. of fall per foot (arithmetic). Stakes carry the cut or fill figure, and each is only as good as the benchmark behind it. Checked Nov. 23, 2026.
What each tool does
| Tool | Job on a patio | Source note |
|---|---|---|
| Grade stakes | Record cut or fill at a point, so the operator digs to a number instead of guessing | Navy engineering training; our grade stakes glossary entry |
| String lines and chalk line | Carry line and slope across the layout; base gravel is screeded or raked to them | Unilock, pp. 4, 14, 19 |
| Level or laser (level reference) | Gives a repeatable height reference from a known point, the benchmark, so each stake is read the same way | General practice; see note below |
| Rod or tape | Reads the height at each point; ADOT takes rod readings to the nearest 0.1 ft | Arizona DOT Construction Manual |
A note on the laser itself: none of the manufacturer pages we could reach published usable figures, so this page gives none. Range, accuracy, self-leveling and grade-slope features vary by model, so read the manual for the one you rent or buy. ADOT also says hand levels are generally limited to inaccessible locations because they are less accurate than an engineer’s level, and it recommends electronic instruments for staking work, which is the logic behind using a laser or builder’s level on a patio.
Set the slope first
Unilock’s patio guide recommends 1.5 to 2% slope, achieved by following string lines when the base gravel is screeded or raked (p. 14).
Percent slope is rise over run. At 1.5%, that is about 3/16 in. per foot; at 2%, about 1/4 in. per foot. Across a 12 ft patio, 2% is about 2 7/8 in. of total fall.
Slope away from the house. Unilock says every installation should slope away from the house; see our base compaction guide for the Belgard figures.
How cut and fill figures get onto a stake
The Navy training manual describes two methods for setting grade stakes. In the first, you turn levels from a benchmark onto the ground beside each stake, reduce the notes to elevations, take the finished grade for each station from the plans, subtract to find the cut or fill, then walk back and mark each stake. In the second, you compute at each station: take the instrument height from the level notes, get the finished grade from the plans, and mark the cut or fill immediately. Fill is marked with an F at the top and numerals for the amount, and the manual says a stake on grade is marked GRADE or GRD. Whichever you use, the figures depend on one agreed reference. If the stake is written to finished surface but you are excavating to the bottom of the base, the base and paver thickness is the difference, so state which one you are marking on the stake.
Protect the stakes
Stakes get hit. ADOT notes that slope stakes in cuts have a short life because of equipment operation, so it sets reference stakes, a guinea driven flush outside the work area with a guard stake behind it, to preserve the position. For a patio, the same idea means setting stakes or offset marks a few feet outside the dig and marking the offset distance on them, then re-checking them against the benchmark when the excavation is half done. If one has been bumped you will find it before it turns into a puddle after the first rain.
A short layout routine
- Mark out the patio area first, and plan the progression of the jobsite before you start (Unilock, pp. 3 and 6).
- Establish one benchmark that will not be disturbed, such as a fixed point on the house foundation, and write down its height.
- Set stakes or offset marks at the corners and along the lines, and record cut or fill at each.
- Run string lines at the finished height and slope, and screed or rake the base gravel to them.
- Check height and slope again after each compacted lift, since compaction lowers the surface.
For the benchmark idea, see benchmark and elevation. For a patio near a house or any drainage change, confirm the grade plan with a professional and your municipality.
Questions
What slope should a paver patio have?
Unilock’s patio guide recommends 1.5 to 2%, with the patio sloping away from the house.
Do I need a laser level to build a patio?
A string line and a level can work on a small flat area, but a laser or builder’s level gives a repeatable height reference over a larger area. Specifications vary by model.
What does C or F on a grade stake mean?
C is cut (dig down) and F is fill (build up). The Navy manual marks fill with an F and the amount.
How do I keep stakes from being knocked out?
Set them or reference marks outside the work area, mark the offset, and re-check them against the benchmark during the dig. ADOT uses guard stakes and reference points for this.
Sources: Unilock, How to Build a Patio on Grade, pp. 3, 4, 6, 14, 19; Navy Training, Setting Grade Stakes; Arizona DOT Construction Manual, Chapter 11, Section 1109. Checked Nov. 23, 2026.
Muthler Landscaping & Construction · Lock Haven, PA
Want it built right?
We build paver patios and walkways in central Pennsylvania, with the grade and base done to the manufacturer’s spec.
Get a quoteAll equipment guidesMuthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.