Perforated drain pipe: slotted vs perforated, sock and wrap
Perforated pipe is drain pipe with openings that let groundwater in (or stormwater out into the soil). The openings can be round holes or slots, and the pipe may or may not be wrapped in a fabric sock. Which combination is right depends on the soil, the job and the spec you are working to.
What “perforated” means
In the pipe industry, “perforated” is the general word and “slotted” is one kind of perforation. ADS, a maker of corrugated HDPE drain pipe, describes its standard Class II pattern as circular and/or slotted openings in the outside valleys of the corrugations, evenly spaced around the circumference and along the length. ADS says perforated pipe is used to speed removal of subsurface water in soils, or to let stormwater percolate into the soil. Solid pipe is the opposite: it carries water from one place to another without taking any in.
The two AASHTO perforation classes
| Item | Class I | Class II |
|---|---|---|
| Shape | Approximately circular, in rows parallel to the pipe axis | Circular and/or slotted |
| Location | Valley of every corrugation, two equal groups on either side of the lower half of the pipe | Outside valleys, evenly spaced around the circumference and length |
| Availability (ADS) | Limited; not available in 4-inch to 10-inch sizes | Standard when perforated pipe is ordered |
ADS also lists minimum Class II open area (inlet area) by size: 0.945 sq in per foot for 4 to 10 inch pipe, 1.42 sq in per foot for 12 to 18 inch, and 1.89 sq in per foot for 24 inch and larger. AASHTO M252 covers 3 to 10 inch corrugated pipe and AASHTO M294 covers 12 to 60 inch.
Slots versus round holes in public specs
Agency specs do not all agree, which is worth knowing before you buy pipe for a job with a spec.
- The Iowa DOT subdrain specification (Section 4143) says longitudinal drains must use slots per AASHTO M252 and that “circular perforations will not be approved.” Its horizontal drains call for three rows of slots about 0.010 inch wide (plus or minus 0.005 inch) on 120 degree centers, with at least 0.75 sq in of slot opening per foot.
- A public subdrainage spec (Section 33 46 00, Subdrainage, revised 2015) allows perforated HDPE with slotted or circular perforations per AASHTO M252 or M294 Class 2, and perforated PVC (ASTM D3034, minimum SDR 35). For PVC with no pattern on the drawings, its default is four quarter-inch holes at 6-inch centers at the quarter points, with no perforations within 6 inches of either end.
Those documents are written for roadway and structure work and are not residential rules, but they show that slot versus hole is a design choice and not a universal answer. If an engineer or the municipality specified a pipe, use that pipe.
Sock, wrap or no sock
A sock is a geotextile sleeve that covers the pipe so fine soil is kept out of the openings. The Section 33 46 00 spec requires all perforated pipe to be wrapped in geotextile with the seams sealed and the fabric held in place during backfill, and it names a factory-installed drain sleeve meeting ASTM D6707 for HDPE pipe. It also pairs the wrap with a clean aggregate envelope: stone no larger than 2 inches with less than 5 percent passing the 3/8-inch sieve. The Iowa DOT plastic pipe section (4146) says perforated corrugated polyethylene larger than 12 inches inside diameter must be wrapped with engineering fabric, while its subdrain section (4143) does not state a sock requirement. In other words, practice varies by agency and soil, and builder guidance goes the other way: Tim Carter advises against a sock on drain tile next to a footing because fabric can trap silt and clog.
What the sources agree on is that the pipe is only part of the system. The stone around it and the fabric (if used) decide whether fine soil can migrate into the trench. Read more on fabric in our drainage geotextile fabric guide.
Which way do the holes face?
The ADS and agency documents reviewed here describe where perforations sit in the pipe wall but do not give a single up-or-down rule for every pipe. ADS Class I puts the holes in the lower half of the pipe; the PVC default pattern puts holes at the quarter points. Builder Tim Carter says to face holes down at the 4 and 8 o’clock positions. Follow the manufacturer’s installation sheet for your exact product.
Solid pipe belongs in some runs
The Section 33 46 00 spec keeps laterals and drain lines that run away from the structure solid-wall, and the discharge end should leave the system through a proper outlet (see drain outlets). Putting perforated pipe where you only want to carry water can leak it right back into the area you are trying to dry.
Check before you dig
Call 811 before any excavation. Stormwater and drainage work can also trigger municipal grading rules and PA DEP requirements, so check with your township or borough and your county conservation district before you discharge anywhere new.
Related
Retaining wall drain pipe and outlets · What is a French drain · Collapsed drain pipe · All drainage guides
FAQ
Is slotted pipe the same as perforated pipe?
Slotted pipe is a type of perforated pipe. Perforations can be round holes or slots, and ADS describes its standard Class II pattern as circular and/or slotted.
Do I need a sock on perforated pipe?
It depends on the soil and the spec. One public subdrainage spec requires geotextile wrap on all perforated pipe, an Iowa DOT section requires fabric on perforated pipe over 12 inches, and builder Tim Carter advises against a sock at a footing. Ask your designer or contractor which applies to your site.
What is the standard perforation class?
ADS says Class II comes standard when perforated pipe is ordered. Class I has limited availability and is not offered in 4 to 10 inch sizes.
Can I use solid pipe for the outlet run?
Yes. One public spec keeps drain lines that run away from the structure in solid-wall pipe, so water is carried out instead of leaking back into the soil.
Sources
- ADS, TN 1.01 Dual Wall HDPE Pipe Perforation Patterns (checked Nov 23, 2026)
- Iowa DOT, Section 4143 Subdrains and Section 4146 Plastic Pipe (checked Nov 23, 2026)
- Section 33 46 00 Subdrainage specification (checked Nov 23, 2026)
- Tim Carter, Ask the Builder, The Spokesman-Review, Dec. 21, 2024 (checked Nov 23, 2026)
Planning information only, not engineering advice. Soil, slope and local rules change what is right for a site; check municipal and PA DEP stormwater requirements and follow your designer’s or contractor’s instructions. Sources checked Nov 23, 2026.