PennDOT Aggregate Acceptance (Pub 408 Section 703.5): Certification, Verification Samples and Pay Reductions

Home / Aggregates / PennDOT aggregate acceptance

PennDOT aggregate acceptance: Pub 408 Section 703.5

Quick answer: Under Pub 408 Section 703.5, construction aggregate normally arrives on certification: the supplier certifies each day’s shipment and runs a quality control plan. PennDOT checks it with verification samples. If the average percent within limits (PWL) falls below 90, certification stops and lot testing starts, and lots that fail can be docked up to 11% of the unit price or rejected.

What certification acceptance means

Section 703.5(a) says certification acceptance applies to construction aggregates, and that AASHTO No. 1 coarse aggregate is accepted under Section 850.2(a)1. Each day’s shipment is certified under Section 106.03(b)3. In plain terms, the producer vouches for the stone, PennDOT spot-checks the producer, and the checking gets heavier only if results slip. The text here comes from the Penn State Aggregate Course Book 2022-23, which copies Pub 408/2020 Change No. 2.

Quality control at the source

The supplier submits a quality control plan for annual review that meets minimum requirements. Stockpiles tested under the plan must be clearly identified, and the producer may add to or ship from them at its discretion. PennDOT then takes three verification samples (n=3) from each tested stockpile, using AASHTO R 90 or a mini-stockpile of about 10 tons. If source or project results show PWL below 90, the Representative orders more source sampling, and no more shipments leave the affected stockpiles until the source results reach PWL 90. If a stockpile is confirmed nonconforming, it is rejected, quality control testing increases, and a new stockpile of 300 to 500 tons (or the remaining Department quantity, if less) is built and tested.

Project verification samples

On the job, samples (n=3) are taken for subbase under roadways and shoulders (Section 350), taken at the point of placement on grade before trimming and compaction, not from project stockpiles unless directed. Other aggregates may be sampled if they look suspect. The inspector tests against Tables C and D, plus crushed fragments from Table B where it applies, and results are due within 5 days. If the average PWL is below 90, certification acceptance ends and lot acceptance starts. Work using that size stops until the Representative sets new lot sample locations and authorizes resumption.

Aggregate quantity (tons)Verification samples (n=3 each)
1,000 to under 2,0001
2,000 to under 10,0002
10,000 to 25,0003
Each additional 25,0001

Lot acceptance after a failure

A PennDOT Certified Aggregate Technician takes an acceptance sample (n=3) at placement for every 7,500 tons placed, and each lot splits into three equal sublots. A leftover quantity under 7,500 tons is treated as its own lot. Locations come from PTM 1, and placement is documented by station. Lot testing continues until five consecutive lots are accepted at PWL 90, after which certification may resume. The contractor is charged for each lot’s inspector testing; the amount in the text is 600, with no currency symbol shown in the extraction.

How a failing lot is paid

Lots at PWL 90 or higher are paid in full. Below that, PennDOT calculates a degree of non-conformance (DNC): for each nonconforming sieve, take the gap between the lot average and the nearest limit and multiply by a factor. Sieves from 4 inch to No. 4 use 1.0, No. 5 to No. 80 use 1.5, No. 100 uses 2.0, and crush count uses 1.0. The No. 200 sieve uses its own table of factors.

Total DNCPay reduction
0.5 to 3.02%
3.1 to 5.04%
5.1 to 8.07%
8.1 to 12.011%
Over 12.0Removal and replacement at no added cost, or left in place at 70% of unit price

Above 12.0, no more material goes on or with the nonconforming material until the Representative decides.

Weighing rules

The supplier prepares weight slips and certifications of accuracy, and names a licensed weigh person as its agent. Scales are calibrated annually by an independent agency the Department accepts, and empty haul trucks are weighed daily unless told otherwise. If an invoice weight exceeds the Department mobile weigh team’s net weight by more than 3%, that is excessive. The supplier must act immediately and, within 30 days of notice, give the District Executive a written description of its corrective actions.

Why a small contractor should care

  • If your stone fails verification, the stop-work on that aggregate size is your schedule problem, not just the supplier’s.
  • Ask for the supplier’s certification and ticket for each load on public jobs.
  • Do not stockpile and re-sell material from a rejected pile.
  • Watch scale tickets. A weight gap over 3% triggers corrective action.

Gaps in what I could read

  • The No. 200 factor table was readable, but its column pairing is easy to misread, so I did not reproduce it.
  • Bulletin 14’s approved source list itself was not in the text.
  • Editions change. The edition in your bid documents controls. For the aggregate size tables themselves, see AASHTO No. 57 and 2A subbase.

Sources

Related

All aggregates · Quality types A, B, C, S · PennDOT 2RC · Anti-skid material

Get a quote

FAQ

What does certification acceptance mean for aggregate?

Each day’s shipment is certified, the supplier runs a quality control plan, and PennDOT checks with verification samples instead of testing every load.

What PWL triggers lot testing?

If the average PWL on project verification samples is below 90, certification acceptance ends and lot acceptance testing begins.

How much can a failing lot be docked?

Pay reductions run 2%, 4%, 7% or 11% by total DNC, and above 12.0 the material is removed or left at 70% of unit price.

How often are lots sampled?

One acceptance sample of three increments for every 7,500 tons placed.

Planning information only. The project specification and your engineer or inspector govern. Source checked Nov. 23, 2026.