Concrete formwork, shoring and precast: what OSHA Subpart Q requires

Quick answer: OSHA’s concrete rules sit in 29 CFR 1926.701 through 1926.704. Formwork must carry all reasonably expected vertical and lateral loads, shoring must be inspected before, during and right after a pour, forms and shores come out only when the concrete has enough strength, and precast lifting hardware must be rated for several times the load. Protruding rebar that workers could fall onto must be guarded against impalement.

Scope of Subpart Q

Subpart Q protects construction workers from hazards in concrete and masonry work. Section 1926.700 defines the terms used, including formwork, shore, reshoring, precast concrete, limited access zone and jacking operation. For footings, slabs, walls, stairs and pads on a residential or light commercial job, the sections most likely to matter are 1926.701 (general), 1926.702 (equipment and tools), 1926.703 (cast-in-place concrete) and 1926.704 (precast). Lift-slab work in 1926.705 and masonry walls in 1926.706 are separate topics.

General requirements: 1926.701

  • Construction loads: no loads may be placed on a concrete structure unless the employer determines, with input from a person qualified in structural design, that it can support them.
  • Reinforcing steel: protruding reinforcing steel that employees could fall onto must be guarded to eliminate the impalement hazard. The section gives no numeric height, so rebar caps or troughs on any bar a person could land on are the usual answer.
  • Post-tensioning: only employees essential to the operation may be behind the jack during tensioning, and signs and barriers must limit access.
  • Buckets: employees may not ride concrete buckets, and no one may work under buckets being raised or lowered. Bucket routing should reduce exposure.
  • Pneumatic placement: workers applying a cement, sand and water mix through a hose need head and face protection.

Equipment and tools: 1926.702

EquipmentRequirement
Bulk cement bins and silosConical or tapered bottoms with a way to start flow; no entry unless the ejection system is locked out and tagged
Concrete mixersLoading skips of 1 cubic yard or larger need a mechanical skip-clearing device and guardrails on each side
Power trowelsManually guided units need a switch that cuts power when the operator’s hands leave the handles
BuggiesHandles may not extend beyond the wheels
Pumping systemsDischarge pipe supports designed for 100 percent overload; compressed-air hoses need positive fail-safe joint connectors
BucketsPositive safety latches on hydraulic or pneumatic gates; buckets must resist hang-up
Bull floatsHandles near energized conductors must be nonconductive or insulated
Masonry sawsSemicircular blade guard with a way to retain fragments

The same section requires lockout and tagout before maintenance on compressors, mixers, screens or pumps, with tags that read “Do Not Start” or similar.

Cast-in-place concrete: 1926.703

Formwork must be designed, fabricated, erected, supported, braced and maintained so it can support all vertical and lateral loads that may reasonably be expected, without failure. Following the standard’s appendix, based on an ANSI form-work standard, is treated as compliance. Drawings for jack layout, formwork and scaffolds must be kept on site.

For shoring and reshoring, the section calls for these steps:

  • Inspect shoring before it is erected, and again before, during and immediately after concrete placement.
  • Do not use damaged shoring that has lost required strength; if damage appears after erection, reinforce it immediately.
  • Use sound, rigid sills, and keep base plates and heads in firm contact.
  • Avoid eccentric loads on shore heads unless the members are designed for them.
  • For tiered single-post shores, keep them vertically aligned, splice them to prevent misalignment, and brace them in two perpendicular directions at the splice level, with diagonal bracing on each tier. A qualified designer is involved for these.
  • Do not adjust shores to raise forms after concrete has been placed.
  • Install reshoring as the original forms and shores come out, whenever the concrete would otherwise carry more than it can.

Other items in 1926.703 cover vertical slip forms, such as climbing rod design and jack capacity limits, and the need to support vertical reinforcing steel against overturning and to keep wire mesh from recoiling.

Removing forms

Forms and shores, other than slab-on-grade forms and slip forms, may be removed only when the employer determines the concrete has gained enough strength to support its weight and any loads on it. That determination rests either on the conditions in the plans and specifications or on compressive strength testing under ASTM standards. Reshores stay until the concrete they support can carry its loads. A cold night or early morning stripping is where this goes wrong, so check mix, temperature and test results before pulling anything on a suspended slab.

Precast and tilt-up: 1926.704

Wall units, structural framing and tilt-up panels must be supported to prevent overturning and collapse until permanent connections are finished. Lifting inserts in tilt-up members must be able to support at least 2 times the maximum intended load, and inserts in other precast members at least 4 times. Lifting hardware must support at least 5 times the maximum intended load. No one may be under precast members being lifted or tilted, except people required for erection.

Field checklist

  • Cap or guard every rebar end a person could fall onto before the crew leaves it.
  • Keep a written record of shoring inspections before, during and after the pour.
  • Do not strip forms on a hunch; ask for the strength basis.
  • Keep non-essential people out from under buckets and precast lifts.
  • Confirm lifting inserts and hardware ratings before the crane hooks on.
Planning information only. This page summarizes public regulation text and is not engineering or legal advice. Formwork, shoring and lifting design belong with qualified people. Check the current CFR text before relying on any number here.

Sources

SourceUsed for
eCFR, 29 CFR Part 1926 Subpart Q, Concrete and Masonry Construction (1926.700 to 1926.706)All sections summarized on this page

Checked Nov. 23, 2026. Check the current CFR text before relying on details.

Related

Masonry wall bracing and the limited access zone · OSHA silica rule for cutting pavers and concrete · Lockout/tagout basics · All PA site work regulations

Talk to us about your project

FAQ

When can concrete forms and shores be removed?

Under 1926.703, only when the employer determines the concrete has enough strength, based on plan conditions or ASTM compressive strength testing, with exceptions for slab-on-grade and slip forms.

Does exposed rebar need to be covered?

Section 1926.701 requires protruding reinforcing steel that workers could fall onto to be guarded against impalement.

What safety factors apply to precast lifting inserts?

Section 1926.704 requires at least 2 times the maximum intended load for tilt-up inserts, 4 times for other precast inserts, and 5 times for lifting hardware.

When must shoring be inspected?

Shoring is inspected before erection, and again before, during and immediately after concrete placement.

General information only, not legal or safety advice. Employers must follow the current OSHA standard and applicable Pennsylvania rules. Source pages checked Nov. 23, 2026.