Proctor Test: Standard vs Modified and What the Curve Shows

A Proctor test is a lab test that finds how much water a soil needs to compact to its highest dry density. The soil is compacted in a mold at several moisture contents, dry density is plotted against moisture, and the peak of the curve gives two numbers: maximum dry density and optimum moisture content. Field compaction is then compared against those numbers.

Proctor test and the terms around it

  • Proctor test: also called a compaction test or moisture-density test. According to a University of Texas at Arlington soil mechanics text, both versions measure the relationship between moisture content and dry density at a specified compaction energy.
  • Maximum dry density: the peak dry density on the compaction curve. Iowa DOT’s method calls it the Proctor density.
  • Optimum moisture content: the moisture content at that peak. See optimum moisture content.
  • Standard Proctor Density (SPD): the benchmark PennDOT’s utility trench guidance uses when it states required density as a percentage.
  • Compaction: the field work the test is meant to guide. See compaction.

Why it matters on a job

Soil does not compact the same way at every moisture level, and every soil has its own best moisture level. A Proctor test turns that fact into a target. Without the test, a density requirement such as “95 percent” has nothing to be a percentage of. With it, the lab report gives a reference value for that specific soil, and field tests report how close the placed fill came. This is why a plan that calls for engineered fill under a slab, a wall base or a driveway may require a Proctor report for the borrow soil. Bearing and settlement depend on that fill. The same logic applies to a subgrade that must carry pavers or concrete.

Standard and modified Proctor

The University of Texas at Arlington text compares the two common versions. Both use the same blows per layer and mold sizes, but the modified test applies much more energy:

  • Standard Proctor (ASTM D698): 5.5 lb hammer, 1 foot drop, 3 layers.
  • Modified Proctor (ASTM D1557): 10 lb hammer, 18 inch drop, 5 layers.
  • Blows per layer: 25 in a 4-inch mold or 56 in a 6-inch mold, for both tests.
  • Mold volume: 944 cubic centimeters, about 1/30 cubic foot, for the 4-inch mold, and 2,123 cubic centimeters, about 1/13.333 cubic foot, for the 6-inch mold.

The text states that the modified test uses a heavier hammer, a higher drop and more layers, so it applies more compaction energy, and it recommends verifying mold volumes before testing. Because the energy differs, the two tests give different results for the same soil, so a specification has to say which test it uses.

What state agencies publish

Iowa DOT’s Instructional Memorandum 309 describes a standard Proctor procedure based on a modified AASHTO T99, Method C. It calls for a cylindrical metal mold about 4 inches in diameter and 4.58 inches high with a capacity of 1/30 cubic foot, and a manual rammer with a 2.00 inch diameter face and a 12.00 inch free drop. The soil goes in as three approximately equal layers with 25 uniformly distributed blows per layer. Specimens are compacted at increasing moisture contents, and the peak of the smooth curve gives the maximum dry density and the optimum moisture content.

PennDOT’s published materials use the same family of tests. A PennDOT compaction presentation lists PTM 106, the moisture-density relations method, as using a 5.5 pound rammer with a 12 inch drop. It also lists PTM 402 for in-place density and moisture by nuclear gauge. PennDOT LTAP Technical Information Sheet 163, Pipe Culvert Trenching and Backfill (Winter 2014), states density requirements as percentages of Standard Proctor Density: at least 95 percent for initial backfill around the pipe, 97 percent for suitable backfill up to 4 feet above the top of the pipe, and 100 percent in the top 3 feet. These requirements are for that publication’s pipe trench context, so check the project documents for yours.

Reading a compaction requirement

Three pieces of information make a compaction requirement complete: the test method (standard or modified), the target percentage, and the moisture range. A note that says only “compact to 95 percent” is missing the first and third. When the soil changes, for example from on-site clay to imported stone, the Proctor value changes too, which is why a new test is tied to each material. Equipment such as a plate compactor does the field work, and the lift thickness matters as well. See fill lift.

Proctor test FAQ

What does a Proctor test measure?

The relationship between moisture content and dry density at a specified compaction energy. The peak of the curve gives the maximum dry density and the optimum moisture content.

What is the difference between standard and modified Proctor?

Standard Proctor (ASTM D698) uses a 5.5 lb hammer dropped 1 foot on 3 layers. Modified Proctor (ASTM D1557) uses a 10 lb hammer dropped 18 inches on 5 layers, so it applies more energy.

What does 95 percent Standard Proctor mean?

It means the field dry density is 95 percent of the maximum dry density found in a standard Proctor test of that same soil. PennDOT’s trench sheet uses percentages of Standard Proctor Density in this way.

How many blows per layer does the test use?

25 blows per layer in a 4-inch mold or 56 in a 6-inch mold, according to the University of Texas at Arlington text. Iowa DOT’s method uses 25 blows per layer in its 4-inch mold.

Sources

Descriptions here are summaries. Verify against the current source and the project specification, which govern.