Free guide · from a working excavation crew
Equipment safety around buried utilities
A bucket tooth does not feel a gas line until it is too late. This is the order we work in before a mini excavator, skid steer or trencher touches soil.
- Call 811 at least three business days before digging (PA PUC).
- Read the marks, then expose the line by careful methods before machine work near it.
- OSHA says contractors must estimate where utilities are and contact the owners before opening an excavation.
- While the hole is open, protect, support or remove lines as needed to keep workers safe.
Our pre-dig checklist
The 811 request is made and the three business days have passed. Marks are on the ground. See 811 for homeowners.
Walk the site with the crew and match every mark to a utility. See the marking colors guide. Anything unmarked or unexplained gets a question before a bucket goes in.
Marks can be off by about 18 to 24 inches, per the PA PUC brochure. Dig the first stretch near a mark carefully and expose the line before the machine works close.
Check overhead lines for boom, bucket and dump-truck clearance. Check where tracks and outriggers will sit over marked lines. Our size data is in the mini excavator chart.
Everyone on site knows where the marked lines run and who stops the machine. One person is the spotter near any line.
Stop work and move people away. For a gas line or any line you cannot identify, leave the area and call 911 and the utility. Do not try to repair it yourself.
What OSHA requires of contractors
Under OSHA’s excavation standard (29 CFR 1926.651(b)), before an excavation is opened the employer must estimate where underground utilities are, such as sewer, telephone, fuel, electric and water lines, and contact the utility owners within their local response times to have the lines located. If a utility does not respond within 24 hours, or cannot pinpoint its lines, work may proceed only with caution and with detection equipment or other acceptable means, and a state or local rule requiring a longer response period overrides the 24 hours. When the dig nears the estimated location, the exact location must be found by safe and acceptable methods, and lines must be protected, supported or removed while the excavation is open.
Common questions
Can I use a machine right on top of a marked line?
Treat marked lines as keep-out areas for machine work until the line is exposed. Marks are an estimate and can be off by about 18 to 24 inches.
Who is responsible if my contractor hits a line?
That depends on the contract and Pennsylvania law. Ask the contractor who makes the 811 call before work starts, and get it in writing. For a dispute, talk to a lawyer.
What if the utility never marked?
Do not dig. Contact PA One Call to follow up on the request. Under OSHA, work can proceed after 24 hours without a response only with caution and detection equipment, and a longer state or local response period overrides that.
Need a machine and an operator who calls first?
Operated excavation by the hour. See Machine Time or call (570) 397-9800.
See Machine TimeExcavation costSources: OSHA 29 CFR 1926.651 · PA PUC, PA One Call · PA PUC 811 brochure
Planning guide, not legal or safety advice. Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584