How to Step a Retaining Wall Base on a Slope
On a sloping grade the blocks stay level and the base steps up. Allan Block and Belgard both say to start at the low end and bury a full block at every step.
To build a retaining wall on a slope, you step the base, you do not tilt the blocks. Start at the lowest point of the wall, set a level base course, then excavate a new level shelf one block height higher and carry on up the grade. Belgard’s Technical Resource Guide says walls built on a sloping grade require a stepped base, and that you should not slope the blocks but step them up so they stay level. Allan Block’s installation page adds the rule that matters most at every step: the block at each step-up must be completely buried to keep the proper base depth.
The two makers agree on the method and differ on a few numbers, so the table below puts them side by side. Your own block maker’s guide wins for your product. For how deep the base goes on level ground, see how deep a retaining wall base should be.
Stepped base rules: Allan Block and Belgard
| Rule | Allan Block | Belgard |
|---|---|---|
| Where to start | At the lowest wall elevation. | At the lowest level, working upward. Dig a level trench into the slope deep enough for the base material and one full block height. |
| How the blocks sit | Each step is level. | Do not slope the blocks; step them up so they stay level. |
| Step height | Not given on the page. Follow the block maker’s guide. | The leveling pad may be stepped up in increments of the block height. |
| Burial at each step | The block at each step-up must be completely buried. | Always bury at least one full unit at each step. |
| Base stone | At least 6 inches of wall rock in the trench, checked for level and compacted with at least two plate compactor passes. | A compacted granular base at least 6 inches deep, of 3/4-inch minus with fines, extending at least 6 inches in front of and behind the first course. |
| Trench depth | 6 inches, plus 1 inch for each 1 foot of wall height, to allow for buried block. | The trench is 6 inches below the bottom of the block and at least 12 inches wider than the block. |
| Drain pipe | At the lowest possible point toward the back of the trench. | Not covered on the pages cited. |
| Slope below the wall | If a slope is present below the wall, contact a local engineer. | Not covered on the pages cited. |
The Stepping Sequence
Allan Block’s order of work for a stepped base, in short:
- Begin at the lowest wall elevation. Dig the base trench deep enough for the base stone plus buried block, and extend it into the slope far enough to bury one full block. Compact and level it with at least two plate compactor passes.
- Put the drain pipe at the lowest possible point toward the back of the trench. Place at least 6 inches of wall rock, check it for level, and compact it with at least two passes.
- Excavate the next step-up, allowing for the base stone and the buried block. Compact and level it.
- Set the base course of block on the base stone and check it for level.
- Fill the hollow cores, the 12-inch zone behind the block, and the next step-up’s base area with wall rock. Backfill with infill or approved on-site soil. Make sure the blocks and the next step-up base are level.
- Compact the wall rock directly behind the block and the next step-up area with at least two passes, then repeat up to the top of the grade, completely burying the block at each step-up.

Why the Burial Rule Matters
Allan Block gives the reason: the block at each step-up must be completely buried to maintain the proper base depth and to prevent wall failure due to erosion. Belgard’s step diagram also labels corner or column units used to maintain bond. Check your own block maker’s guide for how those units are used where the wall changes elevation.
Stepping is how the base follows ground that rises or falls along the wall. A slope below the wall is a separate case: Allan Block’s page says to contact a local engineer. The overall site plan, including how steep the hill is and how the wall is laid out on it, is covered in retaining wall design and in our guide to landscaping a sloped backyard. If the slope is the real problem and you are weighing ideas, see sloped backyard ideas. Water behind a stepped wall still needs a pipe and an outlet; the details are in retaining wall drainage.
Frequently Asked Questions
Can you build a retaining wall on a slope without stepping the base?
Not according to the two block makers cited here. Belgard’s Technical Resource Guide says walls built on a sloping grade require a stepped base, and says not to slope the blocks but to step them up so they remain level. Allan Block likewise has you check that each step-up is level.
How high should each step be?
Belgard says the leveling pad may be stepped up in increments of the block height. Allan Block’s stepping page does not give a step height, so follow the installation guide for your block.
How deep do you bury the block at each step?
Allan Block says the block at each step-up must be completely buried. Belgard says to always bury at least one full unit at each step. In both cases the trench also needs compacted base stone under the block.
Where do you start building a retaining wall on a slope?
At the lowest point. Allan Block starts the base course at the lowest wall elevation, and Belgard says to start at the lowest level and work upward.
What if the ground also slopes away below the wall?
Allan Block’s page says that if a slope is present below the wall, contact a local engineer. It gives no further detail, so treat it as an engineering question rather than a stepping detail.
Sources: Allan Block, Stepping Up the Base; Belgard Technical Resource Guide, page 32; Belgard Technical Resource Guide, page 46.
Published by Muthler Landscaping & Construction, owned by Thayne Muthler (PA HIC #PA212584). How we research and check facts: editorial policy.